How does the XQ-SYSTEM works?
It works very simply; here there's and example of what can you make
with the XQ-SYSTEM, following this procedure:
1 - Make the clearing file for a new yarn style ('EASYPROGRAM' procedure)
Open the "Easyprogram"(1) window, just clicking double on the main menu:
Then, you go to the Iteco clearers to make the clearing program on the new yarn style that you're going to wind; use the 'AUTOCLEARING' function or the 'Manual programming' at your convenience (see Millennium or GOLD leaflet). When the program is released by the clearer, go back to the office and"UPLOAD" (2) the program. Then enter the "Winding machine speed"(3) (mt/min or yard/min) and the "Yarn count"(4) (nm or yard/pound) as well as the "Yarn name"(5) that will be saved as file name. Now you just press a key sending the new program to the group of clearer(6) where the yarn will be wound.
2 - Assign the heads to the operators
Iteco XQ-SYSTEM allows also to check the performance of the winder operators; to do this, the group of heads must be assigned on the SETUP window, to get the aside printout. You'll have a subtotal of the efficiency for every operator(7) and every winding machine(8).
3 - Set up the working shift hours and select the automatic printing out
Thanks to the XQ-SYSTEM, your PC will make automatic printout of the efficiency reports at anytime you would need to have them. The most useful is have 3 printouts : per working shift, per day and per week. Using the Setup window, you can choose when and if getting the above printout. Efficiency graphics, in form of Histograms, can be printed out together with the reports.
4 - Get the efficiency as printing out, graphics and MS Excel files
Once the XQ-SYSTEM prints the report (and the graphics) automatically saves the file into MS EXCEL format (with the date of the file and type of file; es: mux1_shift1_030801.xls) Then you have also the aside
report in your hands with some important information about the performance of your manufacturing as:
- Kilos or Pounds of yarn produced(9)
- Kilos of yarn produced @100% efficiency(10)
- REAL (actual) efficiency in %(11)
- Run time of the heads(12)
Iteco XQ-SYSTEM can be also customised on customer specific demand.
Iteco is always at your disposal to supply tailored designed software to satisfy mill's particular needing. |